The issue is now resolved. What I had to do was assign a 24 hour working shift to a factory calendar, then assign that factory calendar to the shipping point. My issue was that my working shift hours ended at 22:00:00, thus, GI was calculated based on the latest shift possible.
Thank you all for your help.