Hi Jurgen,
Yes, that I can make to setup projects with "non-valuated" stock.But it will help me to some extent only.Because, the project will be accounted at GRN only for these materials but if I want to transfer these materials to different projects, it will not give rise to actual cost on those(receiver) projects (as only quantity movement will be there,hence no accounting entries). It will not allow us to settle our projects individually.
Apart from that, as you said ,
"creating Non-stock materials was the wrong solution., as you could already know from the name that a non-stock material cannot have any stock"
I am still confused on why cant we create material codes for non-stock items? As, when I am creating planned independent requirements (assigning material components to objects like WBS, PM orders etc.) then I am defining material's nature by giving 'item category' of that material and I am procuring Non-Stock items with material codes there.
I am a bit confused on it, please help on clearing my doubt.
Thanks & Regards
Saurabh